JSC ArcelorMittal Kryvyi Rih (Dnipropetrovsk region) has signed an agreement worth almost $30 million with the Chinese company CISDI for the modernization of the largest blast furnace (No. 9).
According to a press release of the company, the contract includes the development of engineering, the supply of basic equipment, its installation, supervision and training of the metallurgical plant’s personnel.
It is noted that the company has four blast furnaces, of which DP-9 is the largest one, its useful volume exceeds 5,000 cubic meters. It produces about half of all pig iron at the steel plant and is still considered one of the largest in Europe.
The modernization of the furnace will increase its productivity to 10,000 tonnes of pig iron per day using the existing raw materials and up to 12,000 tonnes using sinter and pellets. ArcelorMittal Kryvyi Rih plans to produce pellets after the construction of a pelletizing plant (the declared capacity is 4.5-5 million tonnes per year). Both projects are the key ones in the enterprise’s investment program for the renovation and construction of production facilities.
Comments powered by CComment